Mace Dragados HS2 Curzon Street Procurement Pipeline
Package | Procurement commencement | Works Start on Site |
---|---|---|
Precast Concrete Viaduct Beams Supply Only | ongoing | Q2 2024 |
RC Main Works Subs/Superstructure | Q3 2023 | Q3 2024 |
Structural Steelwork | Q1 2024 | Q3 2025 |
Standing Seam Roof | Q3 2024 | Q3 2026 |
Facade – Structural Glazing (East & West Gable End) | Q3 2024 | Q2 2026 |
Façade Systems – Curtain Walling and Glazing | Q4 2023 | Q2 2025 |
Facade Systems – PC & GRC Façade Panels | Q4 2023 | Q2 2025 |
Mansafe System | Q3 2025 | Q3 2026 |
Hard and Soft Landscaping | Q1 2025 | Q2 2026 |
Temporary Electrics | Q3 2023 | Q3 2024 |
Scaffolding | Q1 2024 | Q3 2024 |
Firestopping | Q3 2025 | Q3 2026 |
Architectural Metalwork | Q1 2025 | Q2 2026 |
External Lighting to urban realm | Q3 2025 | Q1 2027 |
Brickwork | Q3 2024 | Q3 2025 |
Fit out (numerous packages) | Q2 2025 | Q3 2026 |
Facade Systems – PC & GRC Façade Panels | Q4 2023 | Q3 2027 |
MEP | completed | Q2 2026 |
Hard Landscaping | Q1 2026 | Q4 2026 |
Soft Landscaping | Q1 2026 | Q4 2026 |
Scaffolding | Q1 2025 | Q3 2025 |
Firestopping | Q3 2026 | Q2 2027 |
Architectural Metalwork | Q1 2026 | Q4 2026 |
External Lighting to urban realm | Q3 2026 | Q3 2027 |
Brickwork | Q3 2025 | Q2 2026 |
Fit out (numerous finishing packages inc dry lining, decorating, ceilings, joinery, shutters, doors, glazed partitions, flooring ) | Q2 2025 | Q3 2026 |
Dock Levlellers | Q1 2025 | Q3 2026 |
Wheelchair and Scissor Lifts | Q2 2026 | Q4 2026 |
RC Main Works Superstructure | Q3 2024 | Q3 2025 |
Structural Steelwork | Q4 2024 | Q2 2026 |
Standing Seam Roof | Q1 2025 | Q2 2027 |
Facade – Structural Glazing (East & West Gable End) | Q1 2025 | Q3 2027 |
Façade Systems – Curtain Walling and Glazing | Q1 2025 | Q3 2027 |
Facade Systems – PC & GRC Façade Panels | Q1 2025 | Q3 2027 |
MEP | completed | Q2 2026 |
Hard Landscaping | Q1 2026 | Q4 2026 |
Soft Landscaping | Q1 2026 | Q4 2026 |
Scaffolding | Q1 2025 | Q3 2025 |
Firestopping | Q3 2026 | Q2 2027 |
Architectural Metalwork | Q1 2026 | Q4 2026 |
External Lighting to urban realm | Q3 2026 | Q3 2027 |
Brickwork | Q3 2025 | Q2 2026 |
Fit out (numerous finishing packages inc dry lining, decorating, ceilings, joinery, shutters, doors, glazed partitions, flooring ) | Q2 2025 | Q3 2026 |
Dock Levlellers | Q1 2025 | Q3 2026 |
Wheelchair and Scissor Lifts | Q2 2026 | Q4 2026 |