Forthcoming Opportunities
Mace Dragados HS2 Euston Station Procurement Pipeline
Package |
Approx Value |
Procurement Programme (CompeteFor posting date) |
Station Works |
RC Station Substructure |
£200-£300m |
Q2 2022 |
MEP for Station |
£200-£300m |
Q3 2022 |
Main Piling Works |
£50m |
Q1 2022 |
Architectural Fit (various packages) |
£100m |
Q2 2024 |
Structural Steelwork |
£25-£50m |
Q1 2024 |
Traction Sub Station Fit Out |
£1-£m |
Q1 2022 |
LU Asset Protection |
TBA |
Q1 2022 |
Green Wall Site Accommodation |
TBA |
Q4 2021 |
Blue Roof |
TBA |
Q4 2024 |
Façade |
TBA |
Q3 2022 |
Precast Concrete Platforms |
TBA |
Q3 2022 |
Brick and Blockwork |
TBA |
Q3 2024 |
London Underground Works |
Asbestos Removal |
TBA |
Q3 2022 |
Interchange Demolition |
TBA |
Q3 2022 |
Interchange Piling |
TBA |
Q3 2022 |
MEP for LU Stations |
£50-£100m |
Q4 2024 |