Mace Dragados HS2 Curzon Street Procurement Pipeline
| Package | Procurement commencement | Works Start on Site |
|---|---|---|
| Precast Concrete Viaduct Beams Supply Only | ongoing | Q2 2024 |
| RC Main Works Subs/Superstructure | Q3 2023 | Q3 2024 |
| Structural Steelwork | Q1 2024 | Q3 2025 |
| Standing Seam Roof | Q3 2024 | Q3 2026 |
| Facade – Structural Glazing (East & West Gable End) | Q3 2024 | Q2 2026 |
| Façade Systems – Curtain Walling and Glazing | Q4 2023 | Q2 2025 |
| Facade Systems – PC & GRC Façade Panels | Q4 2023 | Q2 2025 |
| Mansafe System | Q3 2025 | Q3 2026 |
| Hard and Soft Landscaping | Q1 2025 | Q2 2026 |
| Temporary Electrics | Q3 2023 | Q3 2024 |
| Scaffolding | Q1 2024 | Q3 2024 |
| Firestopping | Q3 2025 | Q3 2026 |
| Architectural Metalwork | Q1 2025 | Q2 2026 |
| External Lighting to urban realm | Q3 2025 | Q1 2027 |
| Brickwork | Q3 2024 | Q3 2025 |
| Fit out (numerous packages) | Q2 2025 | Q3 2026 |
| Facade Systems – PC & GRC Façade Panels | Q4 2023 | Q3 2027 |
| MEP | completed | Q2 2026 |
| Hard Landscaping | Q1 2026 | Q4 2026 |
| Soft Landscaping | Q1 2026 | Q4 2026 |
| Scaffolding | Q1 2025 | Q3 2025 |
| Firestopping | Q3 2026 | Q2 2027 |
| Architectural Metalwork | Q1 2026 | Q4 2026 |
| External Lighting to urban realm | Q3 2026 | Q3 2027 |
| Brickwork | Q3 2025 | Q2 2026 |
| Fit out (numerous finishing packages inc dry lining, decorating, ceilings, joinery, shutters, doors, glazed partitions, flooring ) | Q2 2025 | Q3 2026 |
| Dock Levlellers | Q1 2025 | Q3 2026 |
| Wheelchair and Scissor Lifts | Q2 2026 | Q4 2026 |
| RC Main Works Superstructure | Q3 2024 | Q3 2025 |
| Structural Steelwork | Q4 2024 | Q2 2026 |
| Standing Seam Roof | Q1 2025 | Q2 2027 |
| Facade – Structural Glazing (East & West Gable End) | Q1 2025 | Q3 2027 |
| Façade Systems – Curtain Walling and Glazing | Q1 2025 | Q3 2027 |
| Facade Systems – PC & GRC Façade Panels | Q1 2025 | Q3 2027 |
| MEP | completed | Q2 2026 |
| Hard Landscaping | Q1 2026 | Q4 2026 |
| Soft Landscaping | Q1 2026 | Q4 2026 |
| Scaffolding | Q1 2025 | Q3 2025 |
| Firestopping | Q3 2026 | Q2 2027 |
| Architectural Metalwork | Q1 2026 | Q4 2026 |
| External Lighting to urban realm | Q3 2026 | Q3 2027 |
| Brickwork | Q3 2025 | Q2 2026 |
| Fit out (numerous finishing packages inc dry lining, decorating, ceilings, joinery, shutters, doors, glazed partitions, flooring ) | Q2 2025 | Q3 2026 |
| Dock Levlellers | Q1 2025 | Q3 2026 |
| Wheelchair and Scissor Lifts | Q2 2026 | Q4 2026 |